Central High’s new gym to seat 1,000 fans

CENTRAL HIGH — CENTRAL HIGH — Central High School District is only about one month away from using its new gym. Superintendent Bennie Newton is just waiting for the construction project to be completed and for the keys to be turned over to him.

The gym is the result of a $5.995 million bond issue approved by Central High voters Feb. 14, 2012. A portion of the funds also replaced the Heating, Ventilation and Air Conditioning system (HVAC) in the combined junior high and high school.

“Everybody’s excited,” Newton said. “The more that’s done, the more people get excited. And it’s not just at the school. It’s throughout the whole community as well.”

The project groundbreaking took place in July 2012. Since then, the project has taken shape, with focus now on restrooms and plumbing, and adding the final details.

Newton said some of the details are unique to Central High, to give them the feel of being at the Home of the Bronchos.

The gym has an open lobby separated from the gym floor by a short, rounded brick wall. Above this divide, there is a mural of Bronchos running, which Newton said has been a center of many conversations in the community. There is also a Broncho mural as people enter the front doors of the gym.

“It’s very, very nice,” Newton said. “It’s got some unique things to it. We wanted to have personal touches.”

The new gym will also address some concerns about the current gym. Both gyms will be used which will make athletics and physical education classes easier to schedule. The new gym will also provide more room, including space around the basketball court, which does not exist at the older gym.

Newton said about 1,000 people will be able to attend basketball games, other sporting events or the school’s graduation ceremony in the new gym. The Central High community has 1,194 residents. He said the size of the gym should also make it easy for the school district to host basketball tournaments.

“This will triple capacity of what we have now,” Newton said. “That’s being conservative. It should more than triple capacity.”

Small touches, including digital temperature controls and sensor lights, help bring the new gym into the 21st Century. The locker rooms have speaker volume controls and have a shot clock in sync with the main scoreboard. The scoreboard also contains a video screen.

Newton said the gym will be in use once the project is completed. There are also plans to have an open house following the completion, although a date has not yet been set. And the first high school basketball game set to be played in the new gym should be against Bray-Doyle High School.

“It’s quite an accomplishment for this district,” Newton said. “It shows the support from our community. Our school is what it is because of the support of the community.”

1
Text Only
Local News
  • City Council Water rationing specter suddenly produces a crowd

    The Duncan Council met again on Tuesday, as it does twice a month, but there was something different about the latest gathering -- there were more than a handful of people in the audience.

    July 23, 2014 1 Photo

  • Main Street Duncan receives praise, funding

    Civic leaders on Tuesday endorsed the role of Main Street Duncan in improving the city and urged the council to approve the annual $20,000 contribution it makes to the nonprofit organization.

    July 23, 2014

  • Marlow city council opens fourth firefighter position

    Jason McPherson, Marlow city administrator, announced Tuesday evening that the potential task force for the Marlow fire department did not come together as planned.

    July 23, 2014

  • Stephens County unemployment below the state average

    Oklahoma experienced one of the largest increases in employment in the country for the month of June. The state’s unemployment rate dropped to 4.5 percent, the lowest it has been in almost six years.

    July 23, 2014

  • Community Intervention Center faces budget cuts, layoffs

    While the Duncan Community Intervention Center faces a $126,476 budget reduction next year, it is only part of a $4,977,079 budget reduction by the Oklahoma Office of Juvenile Affairs.

    July 23, 2014

  • Library Teen Volunteers Library shows appreciation for teen volunteers

    To show her appreciation for her summer help, Duncan children’s librarian Darbie LaFontain headed a thank you party for the teen volunteers.

    July 23, 2014 1 Photo

  • School supplies to be given to Velma children

    Velma children may receive free school supplies thanks to the Velma Volunteer Fire Department and the Velma EMS.

    July 23, 2014

  • 7-22 mainstreet.jpg Most Main Street Duncan members haven’t paid dues

    The new executive director of Main Street Duncan has her work cut out for her.
    The nonprofit organization, designed to pump life into Duncan’s historic down, has collected only 40 percent of the dues it is owed for the past year, according to records.

    July 22, 2014 1 Photo

  • 7-22 CTHC Drawing Class2 0288.jpg Phillips leads creative process through Heritage Center art class

    Brenda Phillips took her art knowledge and applied it to two groups Monday.
    Phillips, an art teacher at Duncan High School, led a drawing class Monday at the Chisholm Trail Heritage Center, teaching two groups, youths and adults, the basics of drawing. Phillips will continue the two-day class today.

    July 22, 2014 2 Photos

  • 7-22 Douglass Pool2 0295.jpg Douglass Pool splash pad work underway

    Douglass Pool may be only about a month away from becoming a splash pad.
    On Monday, City of Duncan workers began breaking up the concrete making up the pool deck. Dana Stanley, parks and cemetery superintendent for the city, said he hopes the slash pad project will be completed by the end of August to allow it to be used before the season comes to an end.

    July 22, 2014 2 Photos